As outlined in a recent piece on the Liverpool announcement, PDAs are a collaboration between Homes England, Combined Authorities, the National Housing Bank and other entities to form Joint Delivery Units to theoretically streamline processes and reduce time, risk and cost.
Mid-November has seen five new mirroring initiatives for East Midlands with approximate targets (100,000 homes by 2040), West Midlands (81,000 by 2031), South Yorkshire (17,000 by 2031), West of England (50,000) and the North East (38,000 – no timelines specified), alongside a pledge from Homes England that every Mayoral Strategic Authority will have a PDA in time. It should be noted these targets are approximate and there is supplementary detail associated with most of them.
This all sounds very impressive – but only 208,000 (13.8%) of the 1.5 million homes promised under the Starmer government were delivered in 2024/5. It could be argued that the new PM’s bold devolution agenda could be a catalyst for a significant step change to find a solution. In the words of First Minister Louise Haigh, “genuine and enduring collaboration between public and private sectors is the only way to rewire our economy.” Number 10 North is recognised as the government’s growth delivery unit, and is keen to find ‘enabling partners’ to help get projects over the line. Weightmans would be delighted to be recognised as such a partner.
At present PDAs demonstrate ambition but lack teeth to do what they attempt to promise – deliver. The agreements in themselves do not intrinsically facilitate any planning or funding permissions, resolve any disputes or instruct a single contractor. Obviously, the schemes will be judged on tangible results rather than the nominal strength of partnerships.
Known unknowns
PDAs are very new – as with so much of the governmental architecture of Burnhamism – and so it would be churlish to judge their potential efficacy in haste. However, there are vital questions each area must address and have definitive answers in order to have a degree of certainty they will supply the volume and quality of outlined homes and schemes. For example:
Who bears the cost and delivery risk of strategic infrastructure?
Can planning, transport, utilities and housing investment be coordinated within a single phased delivery plan?
How will benefits along growth corridors between cities, towns and smaller communities be distributed?
Is there a pipeline of sites sufficiently advanced, likely to secure planning consent and able to attract funding to meet the targets?
What specific obstacle is preventing each catalyst site from progressing?
Differential within the PDAs
Variegation and the allowance of difference within guardrails will be a key feature of devolution, and indeed each of the agreements will be looking to solve a range of issues and have different features:
East Midlands: largest PDA according to scale, and most obvious growth corridor-led
West Midlands: most explicit annual delivery benchmark, so associated expectations to deliver at pace according to specific timelines
North East: Has greatest emphasis of wrapping around new transport infrastructure
West of England: Will be sternest test in terms of affordability across small sites
South Yorkshire: Has largest number of previously stalled projects
Liverpool: The original pilot, may be under particular scrutiny given Liverpool City Region’s status as a devolution trailblazer.
Sector response to PDAs
Industry bodies and leading figures have been broadly positive, particularly with regard to greater Mayoral influence over housing investment, creating new regional pipelines and positioning national-level expertise into places which hitherto would not benefit from such attention. It is also anticipated that PDAs will allow earlier and more effective interventions to remove bottlenecks and improve the prospect of attracting private capital.
Will Jeffwitz, Head of Policy of the National Housing Federation, recently commented: “These place-based agreements will help ensure the right homes are delivered in communities up and down the country.” According to Amy Rees, chief executive of Homes England: “Mayors and local leaders know housing and regeneration opportunities and challenges best. The agency’s regional operating model means our teams can provide tailored support to places, including those not represented by mayors, to help deliver against locally driven priorities the length and breadth of England.”
However, faced with sluggish developer markets, rising build and associated costs and other factors outside the immediate control of any Combined Authority or #10 North, rising to these regional challenges will be a tough ask. It would seem – as with other aspects of the new government’s agenda - that diagnosis of problems has been strong, but it remains to be seen if devolution in all its guises will provide sufficiently powerful remedies.
Further issues to address
It should also be borne in mind, especially in light of the Milburn Review, that the sector faces a series of workforce and skillset issues which cannot be resolved overnight which could significantly hamper delivery on the ground, namely:
A shortage of 2,660 town planners in England & Wales (HBF / Paragon, August 2026)
90% of local authority planning departments understaffed (FoI request, as above)
41,200 extra construction workers required per year 2026-30 (CITB)
And so, it is hoped PDAs will meet their lofty intentions and be a panacea to unlock genuine progress across the spine, shoulders and other parts of the country against prevailing trends.